Due to a hick-up with pouring the front steps we've been delayed with framing the posts for the front door are, and delayed the project by a couple of days. Better to have the concrete done correctly than look at a poor job every time we enter the front door of the home.
-Roof shingles are 98% complete waiting for a couple of adjustments on venting
-Windows and doors have presented some problems fortunately the supplier is standing behind all of the hick-ups and we expect to have them 98% complete by the end of the week.
-Plumbing rough-in for supply lines is 90% complete
-BC Hydro finally installed the overhead so we now have power
-Electrical started
-Heating and Venting to start next week, likely Wednesday
-Added tray ceilings to the bedroom & den
-Completed the tray ceiling in the great room
Sunday, October 19, 2014
Thursday, October 2, 2014
Framing & Roofing
The framing of the roof on this one was expected to take two weeks and it seems the estimate was correct, the roof shingles arrived on Wednesday October 1st. We still have considerable framing to complete for the front and rear posts. The windows are arriving today however we are behind on the door sill weatherproofing for the sliders on the rear deck.